← Back to Insights

About this revision

We first published this piece on June 15, 2026 as a pre-deadline explainer. July 4, 2026 has now passed, so we rewrote it on October 10, 2026 to explain how the rules apply to projects today. It is general information, not tax advice — confirm any project’s eligibility with your tax advisor.

The short version

July 4, 2026 did not switch off every commercial clean-energy credit. It split solar projects into two groups under the Section 48E (investment) and 45Y (production) credits:

That is the rule as described in IRS Notice 2025-42, which implements the changes made by Public Law 119-21 (the 2025 budget law often called the One Big Beautiful Bill Act).

“Began construction” has a specific meaning

For solar facilities whose construction did not begin before September 2, 2025, Notice 2025-42 makes the Physical Work Test the only way to establish a construction start — meaning physical work of a significant nature, on site or off site under a binding written contract. Planning, permitting and financing do not count. The older Five Percent Safe Harbor remains available only for low-output solar facilities of 1.5 MW or less.

If you believe your project began construction on or before July 4, 2026, the practical task now is documentation: binding contracts, dated evidence of physical work, and a schedule showing continuous progress toward placing the system in service.

The 30% rate is not automatic

The IRS describes the Section 48E base credit as 6% of the qualified investment, increased up to 30% for facilities that meet prevailing-wage and registered-apprenticeship requirements; the statute also provides exceptions, including for facilities under 1 MW. Bonus amounts (for example, domestic content or energy communities) have their own requirements. And for projects that begin construction after December 31, 2025, new prohibited-foreign-entity (“material assistance”) restrictions apply; the IRS issued initial guidance in Notice 2026-15 in February 2026.

So a credit percentage should come out of a project-specific eligibility review, not be assumed in a spreadsheet. A missing review is not a finding that a project is ineligible either.

Energy storage is treated differently

Notice 2025-42 excludes energy storage technology from the wind and solar facility definitions it applies to, so storage is not subject to the July 2026 / December 2027 solar termination rule. Storage still has to meet the other Section 48E requirements, including wage and apprenticeship rules and the foreign-entity restrictions. In a paired solar-plus-storage project, the solar and storage portions should be assessed separately.

EV charging

The IRS states that the Section 30C credit for alternative fuel vehicle refueling property (which covers EV chargers) does not apply to property placed in service after June 30, 2026.

What to do if you are deciding now

A project that only works because of a credit it may not receive is not a good project. We model the economics on your actual tariff and interval data and show which results depend on tax assumptions.

Sources

Last reviewed October 10, 2026. Tax rules and IRS guidance change; this article is not tax advice.